Yacht Haven Restoration | St. Thomas, USVI
Select another project | See some Past Projects!

click image to enlarge

The marina layout offers 16,000 linear feet of total berthing capacity and incorporates two distinct marina components: one targeted to Megayacht demand, and the other to traditional marina tenants. The Megayacht basin provides flexibility for varying characteristics, including 24 dedicated slips between 80 and100 feet, docks that permit alongside-berthing of vessels of varying lengths (up to 250 feet), enhanced site security, in-slip fueling and Pump out service, high-capacity electrical supply, and segregated docking facilities to provide owners and guests with the level of exclusivity they demand
Provide Engineered drawings with detail for client review including job costing.
Design a state of the art fuel delivery system to meet clients site specific +100 GPM requirements. Provide flow calculations at designated fueling points on new fuel dock and for in slip fueling. Provide a detailed proposal including all costs affiliated with the fuel facility for this project. Drawings were revised by Texaco to meet their specifications and new site specific concerns. Hired by the owners reprehensive to perform on-site consultation for the over seeing of Texaco’s complete fuel facility installation.
Project consists of the installation of five(5) 12,000 gallon double wall storage tanks for diesel and one (1) 10,000 gallon double wall storage tank for gasoline.
The standard speed delivery system has been designed for three (3) public fueling positions along the main dock The High speed delivery system consists of a fueling position for every slip. Sixteen in slip fuel positions will enable all Mega Yachts to fuel while berthed. A custom stainless steel fuel wagon w/ 3” intake hose will be connected at the fueling location closest to the vessel. The connection is to be made to the 3” Kamvalok coupler located within the fiberglass sumps under the dock decking. The fuel wagon will consist of 100 ft of lightweight 2” discharge hose an LC meter and an additional hose reel of 2” x 100 ft hose will be available as required. Operation will be run from a hand held on/off switch which will act in conjunction with all installed E-stops.

 
click images to enlarge
 

Delivery system consists of (5) five 5hp Fe Petro submersible pumps with the a piping manifold for all diesel fueling, Fuel delivery piping +2500 ft of NUPI 4" and 3" for diesel and +1000 ft of 3" NUPI for gasoline. All piping will be installed through 6" pvc sleeves located within each pile cap. All piping, dispenser, and piping sumps will be monitored by a Veeder-root system with the capability of remote readout.

about us | projects & clients | marina fueling/high speed | new projects | links | home

Petroleum Marine Consultants, LLC. | Lic# PC-C056756
Phone: 561-422-9018 | Fax: 561-422-9019 | Email: info@petroleummarine.com

Website design and website hosting by charternet.com